None of them is fabrication. The steel, the welding and the doors account for the number everyone argues about, and the number everyone quotes.
The three lines that decide whether that number holds are buried at the back of the enquiry, phrased as options, and easy to skip. Here they are.
Line one: the coating you thought was cosmetic
A client asks for the enclosure in red, RAL 3000, to match a coating schedule.
On a mild steel structure, that is a paint job. On a 316 stainless enclosure, it is something else entirely — because the standard stainless coating schedule is not a cosmetic topcoat, it is a three-coat system built on the most aggressive surface preparation in common industrial use.
| Stage | Requirement |
| Degrease | Water-soluble degreaser, then fresh water wash |
| Blast | White metal Sa 3 per ISO 8501-1, non-metallic low-chloride abrasive |
| Profile | 35–50 microns |
| Primer | Two-component zinc-free polyamide epoxy, 50 µm |
| Mid coat | MIO-pigmented polyamide epoxy, 125 µm |
| Finish | Aliphatic polyurethane gloss enamel, 50 µm |
| Total | 225 µm dry film |
Three of those requirements exist for reasons that are not obvious, and all three cost money.
Non-metallic abrasive — because steel grit leaves free iron embedded in the stainless surface, and free iron rusts. You get brown bloom on panels that were specified as corrosion-proof, usually within the first wet season, and the client reasonably asks why the stainless is rusting.
Low chloride content — because chlorides on stressed stainless invite pitting and chloride stress corrosion cracking. Blasting a 316 surface with chloride-contaminated grit is a way of starting the failure you were trying to prevent.
Zinc-free primer — because zinc in direct contact with stainless creates a galvanic couple. The primer that protects carbon steel will attack the alloy it is applied to.
Then the arithmetic that matters: you pay by surface area, not by floor area. A 7.3 m × 3 m × 5.2 m unit carries roughly 150 m² of external surface. Three coats at 225 microns over 150 m², with Sa 3 preparation, is a line item measured in thousands of dollars per unit — not hundreds.
And note the trap in how it is asked for: “as an optional offer for the external surface.” Optional makes it feel like a trim. It is not a trim.
Line two: the shipping that isn’t shipping as you know it
Enclosures in this family reach 3.0 m wide and 5.2 m tall.
A standard 40-foot container gives you about 2.35 m of internal width and 2.39 m of door height. The unit does not fit. No amount of careful packing changes that, and no freight forwarder will make it fit.
These units move as out-of-gauge cargo: flat rack where the width allows, break-bulk where it does not. Freight then stops being a line item and becomes a fraction of the delivered price — sometimes larger than the entire fabrication difference between two competing frame designs.
Two consequences worth planning for early:
Agree the shipping method before you agree the price. The method changes the answer. A design optimised for a container that will never be used is money spent on the wrong problem.
Design the lifting and tie-down points for the transport case, not just the service case. A unit engineered to survive a 5 psi blast and then fatigue a seam across three weeks on a flat rack has been engineered for the wrong load. The voyage is not a gap between the factory and the site; it is a load case.
Line three: the sentence at the bottom of the quotation
Every quotation ends with a scope statement. It is the most-read sentence in the document by everybody except the person who most needed it.
Ours reads: this quotation covers the bare enclosure shell only.
What that means, precisely:
- Included — the complete enclosure with its structural frame, doors, roof, platform, ladder, handrails, lifting points and anchorage details
- Not included — the equipment that goes inside: pumps, piping, valves, tanks, controls, cabling
That distinction is the difference between one price and something close to double it. It is also, reliably, the thing a buyer writes back to confirm — and a buyer who does that is a good buyer, because the alternative is discovering the boundary at delivery.
The general rule: the last line of a quotation is a scope boundary, and scope boundaries are where projects go wrong. Read it before you compare two prices, and make sure both prices cover the same box.
The fourth line, less visible
Documentation. For oil and gas work, the paperwork is part of the product: EN 10204 Type 3.1 material certificates traceable to heat number, welding procedure and welder qualifications, inspection reports by the correct method, dimensional reports measured unit by unit.
Then there is the inspection and test plan — the document that sets out who witnesses each check and when they are permitted to stop the job. We have covered that separately. The commercial point here is simpler: third-party inspection is a real cost, it is usually the supplier’s, and it almost never appears in a first quotation.
Budget it at the start. Discovering it at the inspection stage is not a surprise, it is a planning failure.
How to ask for a price that survives
Four questions, in the enquiry, before anyone quotes:
- Is the coating cosmetic or specification-grade, and does it apply to internal surfaces too?
- What is the shipping method — container, flat rack or break-bulk — and who is carrying the freight risk?
- What exactly is excluded from the supply? Name the boundary.
- What documentation and inspection is required, and who pays the third party?
A good supplier will answer all four and put them in writing. A supplier who quotes in a day without asking has given you a number, not a price.